| Project Type: Sound Wall Location: Hamilton Township, NJ Amount: $6.5 million Agency / Client: New Jersey Department of Transportation |
![]() |
![]() |
||||
| Project Description: This project required the installation of 1.51 miles of sound barrier along Interstate 295, including installations each of the cloverleaf ramps of Route 33. Installation included the drilling of 506, 48 diameter reinforced concrete post foundations. The work was implemented so as not to severely impede the flow of traffic and to insure that no ramp was closed to traffic off hours. .Sundry work included concrete barrier curb, two (2) sign structures, electrical lighting, drainage, structure mounted sound wall and landscaping. Year of Completion: 2004 |
||||||